WPWMA C&D Recycling Center Phase 3A & B

Project Overview

Cambridge is the general contractor to complete the renovations of approximately 175,000 sf Material Recovery Facility (MRF).  This includes construction of a new Viewing Platform and coordinating the installation of all new materials processing equipment with Van Dyk, FCC’s equipment vendor.  Outside of this renovation, we are constructing a Covered Aerated Static Pile (CASP) composting system and providing new truck scales and civil construction work including but not limited to a new roundabout at the scale house(s).

Primary Equipment Provider: VanDyk

Client:

Type of Work:

CMAR/GMP